Forterra pushes back £27m factory refurb plan




The masonry products giant said: “In order to de-risk the £27m Wilnecote brick factory refurbishment project, in response to the global supply chain issues limiting the availability of semi-conductors and chips used in the robotic equipment, we have delayed the commencement of the project and temporary closure of the factory by three months.

“The factory is now expected to close at the end of September 2022 rather than at the end of June 2022, with the duration of the project remaining unchanged and the factory due to close for a 12-month period.”

The refurbished factory will produce a wider range of high-end bricks for commercial and specification markets. 

The news was announced in a trading update which confirmed recent price hikes in brick prices of 12% on April 1 and 16% in January.






Grant Prior

Related posts

15-acre Arntz factory site sold to Derry’s Moviebowl owners

scceu

Tennessee factory to become GM’s 3rd electric vehicle plant

scceu

Crayola Draws Snack Deal with The License Factory

scceu