North Sea Saturn Banks gas project in final pre-startup phase

Offshore staff

LONDON – Commissioning has finished of the onshore reception facilities at the Perenco-operated Bacton terminal for IOG’s Saturn Banks gas development in the UK southern North Sea.

Pipeline backgassing is now under way, the final step to first gas which should flow sometime next week, pending weather and logistics.

Backgassing involves reverse flow of gas from the terminal to pressurize the pipeline system to the safe operating window for start-up, with final function tests performed on equipment and safety systems to ensure that forward flow can begin.

3/7/2022

 

 

Related posts

The Iot in manufacturing market size is projected to grow from USD 33.2 billion in 2020 to USD 53.8 billion by 2025, at a Compound Annual Growth Rate (CAGR) of 10.1%

scceu

eClinical Solutions Market Positive Outlook, Revenue Generation & Leading Manufacturers Parexel International Corporation, Oracle, Medidata Solutions, Veeva Systems

scceu

Procure to Pay (P2P) Solutions Market 2020 Global Trends, Share, Growth, Analysis, Opportunities and Forecast To 2026

scceu