Supply Chain Council of European Union | Scceu.org
Procurement

Alberta AG calls for changes to improve infrastructure project procurement

“Proponents invest time and money in the development of their submissions, including their bids, and they rely on and expect fair and competitive procurement processes”

Article content

Alberta’s auditor general has made a series of recommendations for improvements he says are needed to ensure the procurement process for government infrastructure projects is more effective.

Article content

In a report released Wednesday, Auditor General Doug Wylie said some procurement documents are not being posted for the required length of time, the old process confirming that only bids submitted on time are evaluated did not operate effectively and that the government does not have adequate controls to verify that bids comply with requirements.

“Construction contracts are often in the millions of dollars. Proponents invest time and money in the development of their submissions, including their bids, and they rely on and expect fair and competitive procurement processes,” Wylie said in a statement.

“Albertans should be confident that Alberta Infrastructure has effective processes to ensure the significant dollars it spends on construction contracts are procured fairly and competitively.”

Article content

As part of the information gathered from August 2021 to March 2022, auditors found nine out of 17 sampled requests for qualifications RFQs —each with an estimated value of more than $9.1 million — had not been posted for the minimum 25 days required by the trade agreements. Alberta Infrastructure posted three of the 17 RFQs for only 14 days.

According to the report, Alberta Infrastructure receives 17 per cent of bid submissions within one minute of the procurement closing. Auditors found that bid forms were not always accurate and that Alberta Infrastructure accepted hard copy bids that were late before it changed its process to only accepting electronic submissions.

Alberta Infrastructure does not have adequate controls to verify that bids comply with requirements, Wylie said

Article content

According to the report, in eight of the 58 procurements sampled, the bid bond was not issued correctly because the proponent did not use Alberta Infrastructure’s legal name. Those bonds are usually disqualified because there’s a risk that they may not be enforceable but in these cases, only one was disqualified.

“In one case, Alberta Infrastructure awarded a contract with a value between $5 million and $10 million to a proponent
with an improperly issued bond,” the report says.

In another case, the request for proposals included a requirement that bids not be over a certain amount. Each submitted bid was too high but no one was disqualified.

“The contract went to the lowest bidder. A risk exists that the competition may have been limited if some proponents
did not bid on the project as they may have anticipated their bid would exceed the maximum amount stated in the RFP,” the report says.

In the end, Wylie recommended the government put in better controls to ensure compliance with trade agreements as well as improvements for receiving and evaluating submissions.

“Based on our audit criteria, we conclude that Alberta Infrastructure has processes to ensure fair and competitive procurement of its construction tenders but not all of these processes are effective, and improvements can be made,” he said.

Officials with the  Ministry of Infrastructure have yet to respond to questions from Postmedia.

Related posts

Probe reveals flawed procurement, poorly qualified diamond evaluators at state-owned miner Alexkor

scceu

Prabowo’s past US travel ban haunts RI arms procurement – Tue, March 3 2020

scceu

The Implications Of The Covanta Hempstead Case That Expands Beyond County Lines

scceu