Supply Chain Council of European Union | Scceu.org
Freight

Bertling completes tricky power plant deliveries | News

Credit: Bertling

The gas turbine weighed 114.2 tonnes and measured 15.3 m x 5.46 m x 5.18 m. The generator weighed in at 73.5 tonnes and measured 5.8 m x 3.45 m x 2.7 m

Bertling’s scope began by taking over the equipment on a free alongside ship (FAS) basis in Norrkoping and ended with the items being placed on foundations at the turbine hall.

Extremely low water levels on the River Rhine were overcome by means of a specialised barge, which measured 57 m in length and had a 617-tonne payload.

For oncarriage, the cargoes were lifted and loaded onto trailers. Various bridge strength calculations were provided to authorities, and overhead lines lifted to allow passage of the combination. Some traffic flows were rerouted as the trailers navigated the 8 km route to the jobsite, which was performed over two consecutive nights.

At the power plant, the equipment was reloaded onto SPMTs and carefully moved inside the building, before being placed onto their respective foundations.

Related posts

We Are Nearing a Turning Point

scceu

Leased freight ship Valentine permanently added to Interislander fleet

scceu

Digital Freight Forwarder Market Size and Forecast

scceu